NFPA 70E

Arc flash studies in data centers: what's required and when they expire

By Nines Critical · · 5 min read

Short answer: NFPA 70E requires an arc flash risk assessment before anyone works on or near energized equipment, and requires that assessment to be reviewed at least every five years, or sooner when the electrical system changes. The NEC (110.16) requires arc flash warning labels on the equipment. In a data center, the system changes often enough that many studies go stale well before year five.

What an arc flash study is

An arc flash study calculates how much energy a fault would release at each piece of electrical equipment and how far that energy reaches. It typically includes:

  • A short-circuit study: how much fault current is available at each point in the system.
  • A protective device coordination study: how quickly breakers and fuses clear a fault, and whether they trip in the right order.
  • An incident energy analysis: the energy, in cal/cm², a worker could be exposed to at a working distance, and the arc flash boundary.
  • Labels: posted on each piece of equipment so anyone opening it knows the hazard and the PPE required.

The study is engineered and stamped by a licensed professional engineer, based on field data collected from the actual equipment.

Who requires it

  • NFPA 70E (Standard for Electrical Safety in the Workplace) requires the arc flash risk assessment and the five-year review.
  • NEC 110.16 requires arc flash warning labels, with additional information required on larger service equipment.
  • OSHA treats NFPA 70E as the recognized industry practice for electrical safety, so an outdated or missing assessment is an exposure during an incident investigation.

What triggers an update before five years

Data centers rarely stand still for five years. Any of these can change the incident energy at downstream equipment:

ChangeWhy it matters
New utility service or transformerAvailable fault current changes at every point downstream
Added UPS or generator capacityNew sources and new paths for fault current
Changed breaker or relay settingsClearing time drives incident energy
Re-feeds and new distributionLabels may now describe equipment that no longer exists

If the labels don’t match the system, they aren’t protecting anyone, and they may give a worker false confidence.

How to keep it current without a big project every five years

  1. Collect field data when you’re already on site. The same team that performs your infrared scan can verify nameplates, settings and conductor data during the visit.
  2. Track the review date like a certificate expiry. Put it in the maintenance program, not in someone’s memory.
  3. Update after changes, not just on the clock. A small update after a UPS addition is cheaper and safer than discovering the gap at year five.
  4. Budget it across years. Spreading the study cost across an annual maintenance program avoids a large one-time approval.

Nines Critical delivers PE-stamped arc flash studies and updates for data centers, often paired with infrared to share site time. Request a scoping call or read about arc flash studies.

Next step

Tell us about your site.

Send a gear list, a one-line or just the address. We scope it with you, and you get a written scope and price, usually within one business day.