Infrared, arc flash and NFPA 70B

How often should a data center have an infrared scan?

At least once a year, and we recommend twice a year on critical distribution gear. NFPA 70B (2026 edition) calls for infrared thermography of electrical equipment at least every 12 months and shorter intervals when equipment condition warrants it. Most data center operators scan the full electrical path once a year. We recommend adding a mid-year scan of UPS, PDU, STS and busway, the gear closest to IT load.

Do you need an outage to scan our gear?

No. Infrared only works on energized equipment under load, so we scan live. Where covers must come off, a qualified electrician opens the gear under your MOP and NFPA 70E safe work practices. We can supply that electrician, or work alongside yours or your electrical contractor's.

Will you work under our MOP?

Yes. We work under your Method of Procedure, escort and change-control rules. If your site does not have one for infrared, we write a scan MOP for your review before the visit, covering scope, sequence, PPE, roles and back-out steps.

What equipment do you scan in a data center?

The full critical power path: medium-voltage and low-voltage switchgear, transformers, main switchboards, ATS and STS, UPS modules and battery cabinets, PDUs and RPPs, overhead busway and tap-off boxes, generators and paralleling gear. We also scan cooling equipment on request, because some of the most serious findings we see are on compressors and pumps.

What does the report include?

Every inspected component is listed by location, with thermal and visual images for every finding, the measured temperature rise, a severity class from 1 (normal) to 4 (immediate action), and a recommended corrective action. The report is formatted for NFPA 70B records, insurer submissions and audits. Partners can receive it under their own brand.

What is the difference between an infrared scan and an arc flash study?

An infrared scan finds equipment that is failing now: loose connections, overloaded circuits and failing components that run hot. An arc flash study calculates how much energy a fault would release at each piece of gear, so workers know the hazard and the PPE required. NFPA 70E requires the arc flash risk assessment to be reviewed at least every five years. Most facilities need both.

Who signs the arc flash study?

Studies are engineered and stamped by a licensed professional engineer. Our field team collects the equipment data, often during the same visit as your infrared scan, which cuts site time and cost.

How often does an arc flash study need to be updated?

At least every five years under NFPA 70E, and sooner whenever there is a major modification: new utility service, new UPS or generator capacity, a change in protective device settings or a re-feed. Labels must match the current study.

What is an NFPA 70B program and why is it priced annually?

It packages what NFPA 70B and 70E expect into one plan: twice-yearly infrared on critical gear, an annual full scan, arc flash study and label updates on the five-year cycle, and one running record of findings and repairs. Pricing is a fixed annual amount, so the work is budgeted once and does not have to be re-approved every visit.

How often should data center UPS batteries be tested?

Most data centers test UPS batteries quarterly or twice a year, with a capacity test on a longer cycle. For VRLA batteries, IEEE 1188 calls for quarterly checks that include an ohmic reading on every jar, a yearly check of connection resistance, and periodic capacity tests. Wet cell batteries follow IEEE 450, lithium-ion follows the manufacturer's schedule, and the battery manufacturer's instructions come first for every chemistry. You set the cadence; we recommend one based on chemistry, age and how critical the load is.

When should UPS batteries be replaced?

Replace a string when it can no longer deliver 80% of its rated capacity, the industry's end-of-life point, or sooner when jars show a sustained rise in internal resistance, physical damage or leakage. Standard VRLA jars in UPS service typically last three to five years; long-life VRLA and lithium-ion designs last longer. Trended ohmic readings show which jars are aging out, so a single weak jar can be replaced before it takes the whole string down.

Can UPS batteries be replaced without an outage?

Usually, yes. With multiple strings, one string is replaced at a time while the others stay online. Single-string systems are usually moved to maintenance bypass for the swap window. The approach depends on your UPS design and redundancy, so we plan it with your team and write it into the MOP before any batteries are touched.

What is the difference between impedance testing and a load bank test?

An ohmic (impedance) test is a fast reading on each jar while the string stays online. Trended over time, it shows which jars are deteriorating. A capacity, or load bank, test discharges the string at a known rate to measure how long it actually runs. It is the only direct proof of capacity, so it is done at installation and periodically after that, while ohmic testing runs every visit.

Do you service lithium-ion UPS batteries?

Yes. Lithium-ion UPS batteries are managed by a battery management system (BMS), so maintenance centers on downloading and reviewing BMS event and alarm logs, plus physical inspection, connection checks, infrared and module replacement. We also service VRLA, flooded wet cell and nickel-cadmium batteries.

Can an infrared scan tell if a UPS battery is bad?

Partly. Infrared finds hot terminals, loose intercell connections and jars running warmer than their neighbors, which are early signs of trouble. It cannot measure capacity or remaining runtime. That's why we pair infrared with ohmic testing on every visit and capacity testing on cycle.

What happens to the old batteries?

We remove, package and transport them for recycling, and you receive a certificate of recycling for your environmental records. Lead-acid batteries are among the most recycled products in the country, so almost all of the material is recovered.

What do you need to quote UPS battery service?

The UPS make and model, the battery model and quantity, the number of strings, the site location, any active alarms or known issues, and your preferred service window. A photo of the battery cabinet label usually answers most of it.

Can electrical contractors and maintenance providers white-label your work?

Yes. A large share of our data center work is delivered for electrical contractors and maintenance providers under their name and their report branding. We never go around a partner on a site they bring us, and every quote and report for that site goes through the partner.

How is Nines Critical related to InfraredTeam?

Nines Critical is the mission-critical division of InfraredTeam, a Texas infrared thermography firm founded in 1996. Same thermographers, same equipment and the same reporting, focused on data centers and critical power.

Next step

Tell us about your site.

Send a gear list, a one-line or just the address. We scope it with you, and you get a written scope and price, usually within one business day.