Hyperscale campuses, national colocation portfolios, enterprise and telecom sites. Here is what that looks like in numbers, and three programs we run today.
1InfraredTeam founded in 1996. In data centers since 2009.
2Published design capacity of the data center campuses we scan each year, including planned phases. Not measured load.
3Estimate across InfraredTeam, all facility types: inspections × average components per inspection.
4Inspections performed by InfraredTeam since 1996, all facility types.
5States with at least one of our inspections, all facility types.
Inside facilities run by the biggest names in data centers
Work performed directly and through electrical contractor partners. Logos are trademarks of their owners, shown to describe experience, not to imply endorsement.
Programs we run
Three programs, client names withheld.
Data center operators rarely allow vendors to name them. These are real programs with real numbers from our delivered reports. References are available on request once we're under NDA.
Case 01
Hyperscale developer
Three campuses, thirteen buildings, one standard
3
Campuses: DFW, Northern Virginia, Phoenix
13
Hyperscale buildings on rotation
1 wk
Per building, scheduled a year ahead
An annual energized program across a hyperscale developer's campuses in three markets. Each building is scanned in its own week under the operator's MOP, with the same report format at every site so their operations team compares buildings like for like. New buildings are added to the rotation as they come online.
Case 02
National colocation and managed services portfolio
26 sites in 16 states, every year since 2018
26
Sites across 16 states
4,094
Components scanned, 2025–26
90
Findings, 6 urgent or immediate
One thermographic standard across a national portfolio of data centers. Two of the three most severe findings in the last cycle were on cooling equipment, a compressor and a condenser water pump, not on distribution gear. That's why the scope includes mechanical as well as electrical.
Case 03
Multi-site colocation provider, Dallas
Nine years unbroken at the flagship
9 yrs
Annual scans at the downtown site
1,395
Components scanned, 2025–26
7
Urgent findings, 5 on data-floor breakers
Annual infrared across three Dallas-area facilities, with the downtown site scanned every year since 2018. Five of the seven urgent findings in the last cycle were 30A breakers feeding the data floor, the circuits closest to customer racks. Easy to miss one report at a time. Obvious across three sites.
Findings log
A few things we found in data centers this year.
A selection of Class 2–4 findings from our 2026 data center reports, imaged under live load. Site and client names are removed; the state, the asset and the fix are not.
TABLE 01 · FINDINGS LOG · 2026 DATA CENTER REPORTS · SITE NAMES REMOVED
Date
State
Asset
Finding
Class
Action
SEP 2026
TX
PDU
60A branch breaker at 25.6A, failing connection
4 of 4, Immediate
Clean and re-torque
SEP 2026
TX
CRAH
30A feed, all three phases hot
4 of 4, Immediate
Replace components
SEP 2026
TX
CRAH
C-phase lug hot at 15A
3 of 4, Urgent
Re-crimp or replace lug
SEP 2026
TX
RPP
50A branch breaker at 25.1A
3 of 4, Urgent
Replace breaker
AUG 2026
TX
Cooling VFD
Contactor A-phase hot at 52A
4 of 4, Immediate
Clean and re-torque
AUG 2026
IA
Telecom panel
Three 50A breakers at 19–23A
3 of 4, Urgent
Replace breakers
AUG 2026
OR
UPS switchboard
PDU feeder breaker, A and B phases hot
2 of 4, As time permits
Clean and re-torque
JUL 2026
TX
Distribution panel
45A rooftop-unit breaker at 22A
3 of 4, Urgent
Clean and re-torque
JUN 2026
AR
Transfer switch
ATS normal-source A-phase connection, ~139°F
3 of 4, Urgent
Clean and re-torque
MAY 2026
VA
Data hall panel
20A breaker hot at 10.5A
4 of 4, Immediate
Clean and re-torque
MAY 2026
NY
Cooling plant MCC
Condenser water pump contactor, C-phase 309°F
4 of 4, Immediate
Clean and re-torque
MAR 2026
TX
Generator pit panel
Two 30A breakers at 20.7A and 19.6A, 114°F
2 of 4, As time permits
Replace breakers
MAR 2026
TX
PDU
Two 30A breakers at 22A and 20A, 142°F
3 of 4, Urgent
Replace breakers
MAR 2026
TX
PDU
20A breaker at 17A, 131°F
3 of 4, Urgent
Redistribute load
MAR 2026
TX
RPP
Three 30A breakers at 5A, 110°F
2 of 4, As time permits
Replace breakers
FEB 2026
WI
Switchgear
250A breaker, A at 157A vs B at 114A, 115°F
2 of 4, As time permits
Replace breaker, re-torque
How we count
Where these numbers come from.
Big numbers are easy to print. Here is the basis for each one, so you can judge them yourself.
30 yrsOf infrared thermography
InfraredTeam, our parent company, was founded in 1996. Our first data center and telecom inspections date to 2009.
1+ GWOf critical capacity scanned annually
Combined publicly reported design capacity of the data center campuses we scan each year, including planned phases. This is design capacity, not measured load.
500,000+Components scanned
Estimate across InfraredTeam since 1996, all facility types: total inspections multiplied by the average number of components per inspection.
10,000+Infrared inspections
Inspections performed by InfraredTeam since 1996, across all facility types.
45+States scanned
States where our thermographers have performed inspections, across all facility types.
Next step
Want to see a real report?
We'll send a de-identified data center report so you can see exactly what your team would get: every component, every finding, every image.